Lockhart ISD

Lockhart High School Construction Camera

Lockhart High School

Lockhart High School

Lockhart High School was constructed in 1965. There have been numerous additions and upgrades to the facility over the years; however, the campus falls short in a number of areas specific to the size and function of instructional spaces relative to the State standards outlined in the Texas Administrative Code. At almost 185,000sf, the facility supports grades 10th-12th with a current enrollment approaching 1,000 students.

The bond program includes extensive demolition, renovation and additions to the campus to support grades 9th-12th. Also included are improvements to the high school athletic facilities to address capacity and accessibility.

Budget: $47,057,811
Architect:Huckabee, Inc.
Contractor:Bartlett-Cocke General Contractors
Projected Completion: July 2017
Update: Sitework / Misc:
  • Parking lot grading completed; flex base material being installed and compacted
  • Electrician running underground for light poles
  • Sidewalks in courtyard completed
New Construction – Phase 2
  • Section 5 and 6/Common Area/AV Studio:
    • Drywall and tape and bed in progress at the connecting hallways
    • Ceramic wall tile continues
  • Section 7/Performing Arts Center:
    • Electrical rough-in at 50% for the auditorium above ceiling
    • Framing and drywall for the ceiling in progress
    • Lobby tape/float in progress
    • HVAC ductwork 60% complete
    • Canopy roof framing is complete
  • Section 9/Athletic locker rooms:
    • HVAC refrigerant lines tested
    • Plumbing installation at 60%
    • Electrical rough-in at 70%
    • Doors are delivered and installation started
    • Locker concrete bases are formed
  • Section 13/Library:
    • Cabinet installation continues; library desk delivered
    • Painting near complete
    • Carpet tiles installed
  • Section 14/First Floor:
    • Data cabling at the MDF rack in progress
    • Doors and hardware in progress
    • Classroom shelving is staged and ready to start installation
    • Elevator installation at 90%
    • VCT near complete (modifications pending material)
  • Section 18/19/Second Floor:
    • Electrical wiring near complete
    • Science lab gas lines in progress
    • IDF racks completed and cabling continues
    • Painting at 95%
    • Classroom cabinets completed; shelving delivered
    • VCT flooring in progress
  • Section 15/Cafeteria Stage:
    • Electrical rough-in at 70%
    • Ceiling grid installed and lights in progress
    • Rollup doors installed
    • Boring slab beams for plumbing line tie-in
LISD High School 1
LISD high school 2
LISD high school 3
LISD high school 4
LISD high school 5
Looking ahead:
  • Substantial Completion Date – July 20, 2017
  • PAC completion to be September 15, 2017